Your Critical Path Blog

Delay Damages: Home Office Overhead Formulas 2 of 4 (Canadian & Hudson Formulas)

August 27, 2018

This posting introduces the Canadian and Hudson Formulas and discusses how they are used to calculate a contractor’s home office overhead costs for a project that experienced an excusable and compensable delay.

Like the Eichleay Formula, the Canadian and Hudson Formulas calculate a contractor’s home office overhead damage amounts by calculating the project’s home office overhead daily rate and multiplying that rate by the compensable days of delay to calculate contractor’s home office overhead damage amount.

However, unlike the Eichleay Formula, which calculates the subject project’s share of the company’s home office overhead costs based on a percentage of revenue, the Canadian Formula relies on the contractor’s actual overhead markup percentage. The markup percentage can be either the contractor’s planned home office overhead markup percentage supported by its bid documents or its actual home office overhead percentage calculated by an audit of the contractor’s records. The formula is depicted below.

Canadian Formula

An example using the Canadian Formula to estimate a contractor’s home office overhead compensation for a 50-day compensable delay is below.

The Hudson Formula is nearly identical to the Canadian Formula. However, while the markup percentage used in the Canadian Formula only compensates the contractor for its overhead costs, the Hudson Formula’s markup percentage includes both overhead and profit.

For more on this or any other topic, please call me at 215-814-6400 or email me at mark.nagata@traunerconsulting.com.

Delay Damages: Home Office Overhead Formula 1 Of 4 (Eichleay Formula)

August 13, 2018

In the previous posting, I identified five home office overhead formulas (Eichleay, Canadian, Hudson, Manshul, and the Specified-Rate Formulas) that are used to determine a contractor’s home office overhead damage amount.

Each of these five formulas determine the contractor’s home office overhead percentage in different ways and for different reasons, which, in turn, can result in significantly different damage amounts.  This and the next couple of postings will describe each of the formulas, their differences, and why they calculate different damage amounts.

The most commonly-known home office overhead calculation method is the Eichleay Formula.  The use of the Eichleay Formula was established by an Armed Services Board of Contract Appeals decision in 1960.  The project involved the construction of a Nike missile site and the contractor was the Eichleay Corporation.  The formula that was used by the board to calculate the Eichleay Corporation’s unabsorbed home office overhead cost has become known as the Eichleay Formula.

In federal contracting and in many state courts and other jurisdictions, the Eichleay Formula is a well-established method to calculate a contractor’s unabsorbed home office overhead amount.  However, refinements governing its use seem to accompany each new ruling.

When applying the Eichleay Formula, some courts and triers of fact require that a distinction be made between (1) unabsorbed overhead versus extended overhead and (2) delays caused by additional work versus delays caused by suspensions. Additionally, when using the Eichleay Formula to calculate a contractor’s unabsorbed home office overhead costs, some courts have generally required that the contractor must establish

Delay Damages: Do You Have Unabsorbed Home Office Overhead Cost?

July 30, 2018

Unabsorbed home office overhead is a well-known, but not well-understood delay damage and, like extended field office overhead, is only recoverable by a contractor after experiencing an excusable, compensable delay.  Home office overhead costs include, but are not limited to:

  • Home office rental or home office ownership costs,
  • Insurance costs that can’t be assigned to a specific project,
  • Home office utilities and telephone,
  • Home office equipment and maintenance, and
  • Salaries of home office staff (company officers, estimators, payroll clerks, receptionists, and others not assigned to a specific project).

Home office overhead costs are indirect costs that a contractor incurs, which are necessary to support all of the contractor’s projects, but are not directly chargeable to any particular project. Typically, the contractor’s home office overhead costs are apportioned or distributed among all of its projects.

Rather than using the term unabsorbed home office overhead, some use the term “extended” home office overhead.  More often than not, while there is a distinction between these terms, the two are often used interchangeably.  Resolving this issue is beyond the scope of this article, but for the purposes of this article we will use the term unabsorbed home office overhead.

This term is used because payment for home office overhead is typically based on an “underabsorption” argument, not an “extension” argument.  For example, consider the cost of the contractor’s Chief Financial Officer. The cost of the CFO is not “extended” if one of the contractor’s projects

Delay Damages: Calculating Extended Field Office Overhead Costs

July 16, 2018

Perhaps the most common delay-related cost alleged in claims, and as part of time extension requests, is one that focuses on extended field office overhead and job supervision costs. As we know, construction projects require field office labor and equipment to be maintained throughout the duration of the project, but those costs are not necessarily chargeable to a particular item of work. These costs are what we call “time-dependent” costs, and include things such as job site trailers, sanitary facilities, office equipment, security resources, phone/electrical/water services, and salaried job supervision personnel such as project managers, project engineers, superintendents, and administrative staff.

Naturally, when a project is delayed, these time-dependent costs will be required to support the project for a longer time period, and will cost a contractor more than what was anticipated in its bid. The question is – what is the proper way to calculate and account for these increased costs?

Often, both owners and contractors will take the simplest, albeit the least persuasive, way to calculate their field office overhead costs by establishing one field office overhead daily rate for the life of the project. This often results in an amount that is either more or less than the proper amount that should apply for the period in which the delay was experienced.

A contractor’s daily rate for field office labor and equipment is generally not linear over the life of the project. Rather, these costs typically follow a curve as they build up during the initial phases of the project,

Delay Damages: What Is Extended Field Office Overhead?

July 02, 2018

Field office overhead is perhaps the most well-known and well-understood type of delay damage. A contractor only incurs extended field office overhead costs when the project is critically delayed and when the project’s duration is extended.

Field office overhead costs consist of indirect costs that are incurred and necessary to support the project work at the field level and that are directly chargeable to the project. Field overhead costs include, but are not limited to:

  • Field office rental
  • Salaries of field office staff
  • Field office staff vehicles
  • Field office utilities and telephone
  • Field office consumables

Extended field office overhead costs (also called jobsite overhead costs) are, by definition, costs that increase due to a critical delay. For example, if the project is delayed a month, then the contractor would incur additional time-dependent field office overhead costs such as the rental cost of the field office, the salaries of field office staff, and similar time-dependent costs incurred to support the contractor’s operations in the field for the project’s additional month of duration.

The contractor’s entitlement to payment for extended field office overhead costs is based upon the presumption that its original contract price only included field office overhead costs needed to support the project during the original project duration. So, when the project duration is extended, the contractor would incur additional field overhead costs to support the project.  If the extended project duration was caused by an excusable and

What Are Delay Damages?

June 18, 2018

Your Critical Path Banner

 

Although the term “delay damages” is often referred to in construction change order requests, requests for equitable adjustments, and claims, it is often misunderstood or not properly defined. So, what exactly are “delay damages?”

Unfortunately, the answer to this question is not as simple as you may think. It’s reasonable to conclude that the term “delay damages” is simply defined as “damages that are caused by delay.” But this definition depends on the how one defines the term “delay.”

For example, when the term “delay” is defined as only critical project delay (a delay that is responsible for extending the project’s duration), then the term “delay damages” is often narrowly defined as only the damages that result from the project’s extended duration.

The damages that would result from a critical delay include the following full complement of delay damages:

  • Extended field office overhead
  • Unabsorbed home office overhead
  • Liquidated damages
  • Idle labor and equipment costs
  • Labor and material cost escalation
  • Other costs

If delay is defined as both critical and non-critical delay (a delay that is not the cause of an extended project duration), then some, not all, of the potential delay damages above may be recoverable.  Because a non-critical delay does not extend the project’s duration, extended field overhead costs

Recommended CPM Schedule Update Submission Items

June 04, 2018

 

Your Critical Path Banner

 

While the previous posting described the importance of updating the project schedule, this posting identifies essential project schedule information that should be included in a schedule update submission. Clear and timely communication is a key contributor to success on construction projects. These recommended schedule update submission items will ensure that the contractor is effective in communicating its plan for completion, and will promote an environment of trust, transparency, and confidence among the project team.

A contractor’s schedule update submission should, at the very minimum, include a detailed narrative, the native electronic schedule file, and a small collection of printouts. Each of these items is discussed in more detail below.

Detailed Schedule Update Narrative

A properly prepared and detailed update narrative is a valuable tool not only for the contractor, but for the entire project team. By identifying the project’s current status, critical path, and forecast completion dates, and by describing the project’s current problems, upcoming issues, and potential solutions to those problems and issues, the update narrative can be a vital communication vehicle for the project team.

Although the reporting of unresolved change orders, delays, and other project issues in the update narrative may not satisfy the contractual, statutory, or legal notice requirements, reporting of these issues in the update narrative, on at least a monthly basis, should serve to ensure that the project team was aware of these

Don’t Forget to Update Your Project Schedule or (Don’t Neglect Your Project Schedule)

May 21, 2018

 

Your Critical Path Banner

 

On construction projects, time equals money. When construction projects finish late, both contractors and owners potentially incur additional, unanticipated time-related costs. It often happens that well before the project actually finishes, the project team is aware that the project will finish late. A properly updated project schedule is the only time-management tool available to the project team that can reliably forecast the project’s late finish date.

Unfortunately, toward the end of projects, as the pace of work intensifies and as the project team focuses their efforts on solving problems and completing the work, the project schedule is too often ignored. As a consequence, the project schedule is not updated and submitted on a monthly basis, as required by the contract or per project schedule management best practices.

Just as a properly updated project schedule is the only project management tool that forecasts when the work will be complete, it’s also the only time-management tool on the project that can be used to reliably identify and measure how, and to what extent, the project was delayed.

Predictably, and as Murphy’s Law dictates, the project is nearly always delayed whenever the project schedule is not updated and submitted. Therefore, to ensure that the current schedule update always represents the current plan for completion, contractors should also prepare and submit periodic schedule updates in accordance with the contracts. Additionally, contractors should

Construction Delay Analysis – Principle No. 5 of 5

May 07, 2018

Delay Analysis Principle No. 5:

Activity delay and project delay are not the same thing.

Too often, contractors and analysts submit time extension requests, or delay claims, that attempt to measure or calculate “project delay” by comparing how much later an activity starts or finishes, compared to when it was depicted to start or finish in the project’s schedule, without regard to whether the activity is even on the critical path.

As noted in Delay Analysis Principle No. 1, and reiterated in Principle Nos. 2 through 4, “only delays to the project’s critical path will delay the project.” The proper way to think about activity and project delay is that a delay to a critical activity is what causes the delay to the project. Conceptually, activity delay is the “cause” and the project delay is the “effect.”

So, when a critical activity starts late, finishes late, or progresses more slowly than expected, that activity delay could cause a delay to the project’s completion date, which is the “project delay.” It is this project delay that is the ultimate result of a critical activity’s late start, late finish, or slow progress.

More importantly, when a project includes an incentive/disincentive clause or a liquidated damages clause, the payment for the earned incentive, the assessment of the disincentive amounts, or the liquidated damages are calculated from a specific contract milestone date. Therefore, when calculating project delay to a specific contract milestone, the analyst should calculate the delay by measuring how many days late the milestone

Construction Delay Analysis – Principle No. 4 of 5

April 23, 2018

Delay Analysis Principle No. 4:

The critical path can and does shift.

No matter how large or small your project is, no project is built “exactly” as it was planned. You’ve heard the cliché: the best-laid plans of mice and men…. No matter how carefully a project is planned, it is impossible to predict every problem or obstacle that might be encountered. To address these challenges, we need a project scheduling tool that we can adjust to the ever-evolving project conditions.

Similarly, even if a contractor was able to prepare the best possible construction plan and schedule, the plan will change or need to evolve in response to things like weather, design changes, and subcontractor performance issues over the duration of the project. The only constant in life and construction is change. In fact, construction contracts are specifically written to deal with unanticipated changes as they arise.

If we accept that the contractor’s construction plan will change over the course of the project, then the natural extension of this concept is to accept the fact that the critical path is dynamic in nature and may change, or shift, during the project in response to the project’s changing conditions.

Shifts to the critical path depend on how the project is planned; how the project work progresses or does not progress; and the changes that are made to the schedule logic and activity durations.

When managing a project, it is essential to identify when the critical path changes, or shifts, to make certain that

Page 3 of 4«1234»