Client: New York State Department of Transportation
Market Segment: Transit/Transportation
Services Provided: Owner's Representation, CPM Scheduling, Claims Analysis & Dispute Resolution
Location: Suffern, NY
Project Value: $97,000,000
Trauner was initially retained by the New York State Department of Transportation (NYSDOT) to assist the replacement construction manager in completion of this troubled project. Allegations of inspector fraud concerning pile driving were a component of the problems on the project.
Trauner provided construction scheduling and claims management. Specifically, our services included a review and analysis of contractor's Critical Path Method schedule, revisions to project reporting systems to accurately document manpower and equipment utilized and work performed, analysis of as-planned versus as-built schedule and analysis of liability related to time extensions, acceleration, and extra work.
Trauner assisted NYSDOT in project closeout. In addition, we assisted NYSDOT in the analysis of project time extensions requested by the Contractor on the project.
Back to Project List
|